Turnkey - EPC
As an engineering company, we are dedicated to offering technical solutions for energy efficiency.
Our commitment is to turn every challenge into an opportunity to improve the efficiency and sustainability of our clients. Below is a summary of our “FCC Unit Heat Recovery Boiler” project, which serves as a sample of our methodology and the scope of our capabilities in various phases of an EPC project.
Project summary
The FCC Unit Heat Recovery Boiler project carried out by AITESA consisted of a turnkey project (engineering, design, manufacturing, supply and assembly) at a Spanish refinery located in San Roque, Cadiz, Spain.
The objectives were to improve the annual efficiency and availability of the boiler.
This new boiler replaces and improves upon an existing boiler, which had multiple problems resulting in low efficiency and low annual availability.
Engineering disciplines involved
Process engineering
Analysis begins with a thermal balance between the thermal power available in the hot fumes and the expected steam generation. Once the steam generation is validated, the thermal design of the equipment is carried out. From this phase, the unit equipment is defined in terms of size, number and arrangement of tubes, material specification and type of fins required which allow the recovery boiler to operate under the established conditions and offer the required performance. A rigorous sizing model is used for this purpose including :
- Mechanical:
- Materials and dimensions identical to those to be used.
- Process :
- Flow rate and flue gas composition
- Water/steam flow rate: Resulting from the heat balance.
Technical office
Definition and delineation including development of general arrangement and layout drawings to detailed drawings for unit equipment, piping and ducts for both air and hot fumes.
Structural engineering
Structural engineering included all load calculations to define the support structure for all boiler elements including access with stairs and platforms.
We performed detailed calculations to ensure the integrity and safety of the structures, adapting them to the new operational requirements.
Instrumentation and control
Development of process and instrumentation diagrams(P&IDs) and process flow diagrams(PFDs) that describe in detail the instrumentation and equipment for process control.
The lists of lines, instruments, manual valves, process control valves and signal lists enables development of system control logic.
Electricity
In this phase the low voltage electrical engineering is performed. Power supply to the electrical consumers is defined for equipmnet including soot blowers, sealing air fans, all motors and pumps, and lighting.
Definition and routing of power cables to serve the consumers, as well as the definition of grounding networks, switching stations and junction boxes is included.
Civil works
During the civil works phase, a geotechnical study of the area where the boiler would be installed was carried out to analyze the composition of the soil strata. In the area there was an existing concrete slab and pillars, which required demolition. With the loads transmitted by the new boiler at the support points, the calculation of the new slab with the necessary pillars and the support plinths for the pumps was carried out. The works for the execution of the new slab would include excavation of the ground, backfilling with new concrete, reinforcement of existing and new and concrete pedestals to receive the structure, backfilling with gravel and replacement of the pavement.
Quality
Continuous review of all materials, manufacturing procedures, manufacturing progress and final dossiers.
Procurement
Procurement management involved the preparation of requisitions for request for quotations (RFQs), technical-economic tabulations and the preparation of technical and economic evaluation reports.
These processes ensured the acquisition of the best equipment and services, optimizing the cost-benefit ratio.
Construction
The construction and assembly phase included the management of all subcontractors on site, namely civil works, mechanical assembly, electrical and control and instrumentation installation and thermal insulation.
Good coordination of the tasks of all subcontractors resulted in greater efficiency in the work and greater success in meeting completion dates.
Upon completion of assembly, the pre-commissioning (cold), commissioning (hot), performance testing and start-up of the new recovery boiler took place.
Talk to an expert
Aitesa has more than 40 years of experience designing and supplying heat recovery boilers.